Transfer heights between modules in a complete bottling line

Use an interface sheet to compare transfer heights and datums between existing and used bottling-line modules.

Italiano

Two bottling machines can each be suitable for the package and still meet at different levels. Catch that gap before the order by measuring the bottle-support surface on both sides of each handoff. A shared floor reference and photographs make the readings comparable when the machines sit in different buildings or their original feet are set at different heights.

Set the measurement reference

Mark the proposed finished-floor plane on the layout and number the transfer points in flow order. For each, identify exactly what is supporting the bottle at the boundary. On a belt conveyor that can be the top of the belt. A neck-supported section needs its own datum at the contact point. Record the package reference, current leg position and whether the figure was measured or copied from a drawing.

Use this interface record

One row per physical connection. Record millimetres consistently and attach a photo identifying both measured surfaces.
ConnectionUpstream height and supportDownstream height and supportOwner, evidence and decision
Depalletiser to empty-bottle conveyor_________
Empty-bottle conveyor to rinser or filler_________
Filler discharge to downstream conveyor_________
Labeller to case packer infeed_________
Case packer discharge to palletizing section_________

Turn the gap into a documented scope

As an illustrative calculation, an exit at 1,050 mm and an inlet at 1,025 mm differ by 25 mm when measured from the same floor plane. The difference is a survey result. Ask the integrator to determine what transition is acceptable for your equipment and container, including the guide alignment, allowable adjustment range and the space needed for turnover or bypass. Where a transition component is needed, include its supplier, drawing reference and test criterion in the quotation. Confirm the raised or lowered segment also works for the planned operator and service clearances.

Complete line handover and interface guide

Compare the line with your installation

Send a layout, measured handoffs and the package formats that will run. Include the intended locations of used and retained modules.

Record the measured datum and the support reference before machinery is taken apart. The complete line relocation guide explains which evidence to carry into reassembly.