Choose transport sections with the dismantling and receiving teams. Start from the layout and identify separable module boundaries. Ask the responsible specialists to confirm weight, dimensions and any installation or lifting requirements. Give every planned section a reference.
Keep reconnecting evidence with each module
Record what is split at its interface, how attached items are labelled and what stays at the original site. Confirm with the receiving installer which connections and checks it will need. Keep the packing list linked to the marked drawing and photos.
| Field | Evidence | Assigned to |
|---|---|---|
| Section identity | Drawing and unique mark | ___ |
| Transport envelope | Dimensions, weight and load plan | ___ |
| Connections at split point | Photo and included parts | ___ |
| Reassembly evidence | Receiving list and test owner | ___ |
If a bottle transfer crosses a proposed transport split, capture the location of the guide faces and the interfaces on both sides before separation. Put the identifiers of both sections on the reference photograph. At the destination, use that record with the supplier’s approved alignment check before approving the handoff.
Plan the dismantling and relocation of a complete line
Review the planned transport sections
Share layout, site constraints, expected modules and destination.