A depalletiser may support two lines on average and still run short when both request containers simultaneously. Use peak windows from the two production schedules and the actual pallet format. Make the routing, buffer and changeover assumptions visible before adding the second branch.
Record the simultaneous-demand scenario
Use the same unit and window for both lines. Record containers per pallet, format changes and feasible buffer at each destination. Agree which line takes priority if both branches request a pallet or one branch cannot accept its supply.
| Observation | Illustrative input | Check on site |
|---|---|---|
| Line A demand | 4,800 bottles/hour | ___ |
| Line B demand | 3,200 bottles/hour | ___ |
| Pallet size for this example | 960 bottles | ___ |
| Combined demand at peak | 8.33 pallets/hour | ___ |
| Confirmed depalletiser output and change time | ___ | ___ |
The combined rate is 8,000 divided by 960. Over 15 minutes that is about 2.08 pallets of demand. Use the actual buffer positions, whole pallets and intervals to simulate the next request, especially during a format change at one line.
Define the boundaries between the depalletiser and both lines
Check a shared depalletiser against both schedules
Send the two outputs, pallet details, format-change windows and equipment layout.